Projects Currently Underway

Cleveland Street Reconstruction Project


This project was awarded to All American Concrete of West Liberty, Iowa, on July 20, 2017, in the amount of $403,889.10.  The project will begin Monday, Aug. 14, 2017, and consists of removing and replacing existing concrete on Cleveland Street from Park Avenue to 2nd Avenue. There will be access provided to businesses at all times. However, there may be some delays. Please be patient. Contract completion date is September 30, 2017. Contact City of Muscatine Public Works at 263-8933 if you have any questions. Pictured below is a guide to the four phases of the project. However, the schedule is not cast in concrete and is contingent upon the requirements of the contractor. The phases may change as needed.

Phases Of Construction

Update as of August 17, 2017:
Phase I of the reconstruction project replaces the pavement from Park Avenue to just east of the west entrance to McDonald's off of Cleveland Street. That west entrance remains open. McDonald's also added a temporary entrance to the north side of the restaurant off of Frontage Road. All American Concrete began removing the pavement on Tuesday, Aug. 15, and is currently grading the section to prepare for pouring concrete. Phase II of the project is scheduled for the section from 2nd Avenue to just west of Coventry Lane.


West Hill Sewer Separation Project - Phase 3


Phase 3 project was awarded on April 16, 2015 to Hagerty Earthworks, LLC of Muscatine, Iowa in the amount of $4,988,688.00.  

Update as of August 17, 2017:  

The focus of the contractor is up around 4th Street Park. The contractor is working on the sanitary sewer services on the west side of 4th Street Park at 4th & Broadway and has made it up to Cherry Street. The intersection of Cherry and West 4th is now closed. The paving contractor is finishing the concrete work at the West 4th/Locust Street intersection. Grading for paving is occurring now on Broadway between the #3 and #4 alleys on the east side of the park. Broadway between the #3 and #4 alleys will be paved in the near future. Once the sewer contractor finishes the sewer work up to Cherry and another short section on Cherry Lane they will move down to East 5th to do their sanitary sewer replacement work between Cedar Street and Iowa Avenue.

Muscatine Power and Water will be closing East 5th at the intersection with Cedar to replace the fire hydrant there. This closure will begin either Friday, August 18 or Monday, August 21.

Click here for more information.


Asphalt Overlay Program 2017



Bids were accepted and a contract was awarded to Illowa Investments, Inc. of Blue Grass, IA on July 20, 2017 in the amount of $519,250.10. Work is expected to begin the third week of September 2017. 

The list of proposed streets for 2017 follows:
Elfers Street from Grandview Avenue to Dead End
Washington Street from Diagonal Street to River Road
McArthur Street from Lincoln Boulevard to Summit Avenue
Jefferson Street from Lincoln Boulevard to Fillmore Street
Isett Avenue from East 11th Street to Woodlawn Avenue
Cypress Street from East 11th Street to #9 Alley
Howard Street from Clay Street to Jackson Street
Eisenhower Street from Devitt Avenue to Dead End
5th Avenue from Webster Street to Blaine Street
Lincoln Boulevard from Clay Street to Lake Park Boulevard
57th Street from 67th Avenue to rail road tracks 
 

Sidewalk Program 2017


The 2017 Sidewalk program has not been formalized as yet and will be completed in the spring of 2018.